Regulator / Spillway gates at Chute-Allard Power Plant

La Tuque, Quebec, Canada

Description

Central Chute-Allard is a hydroelectric power plant and a dam built on the Saint-Maurice River by Hydro-Quebec, near Wemotaci in the administrative region of Mauricie, in Quebec . Cette centrale, d’une puissance installée de 62 MW et la centrale des Rapides-des-Cœurs , située en aval , ont été mises en service en 2008 . This plant, with an installed capacity of 62 MW and Rapides-des-Coeurs , located downstream , was commissioned in 2008.Leur construction a été complétée en 2009 . Construction was completed in 2009.

A leading resource of Progesys offered its services for Design and Supervision activities, regarding Spillway/Regulator gates, embedded parts, Hydraulic Hoist and Support Structure.

Information

  • Year of realization : 2008-2009
  • Project value : USD 20 Million$

Services offered

  • Design & Calculations
  • Detailed engineering and drawings
  • Redaction of fabrication and installation procedures
  • Supervision of fabrication and installation